No |
Description |
Scope of Work |
Location |
Owner |
1 |
Erect 1 Unit of 70 MW Steam Turbine & its equipment & piping works for Co-gen SC-4 |
Mechanical & Piping |
Serang |
PT. Indah Kiat Pulp & Paper |
2 |
Erect 1 Unit of 70 MW Steam Turbine & its equipment & piping works for Co-gen Plant TK-3 Tjiwi Kimia |
Mechanical & Piping |
Mojokerto |
PT. Tjiwi Kimia |
3 |
Erect 1 Unit of 45 MW Steam Turbine & its equipment/piping works for 2nd part of CCCP Plant Sengkang, South Sulawesi |
Mechanical & Piping |
Sengkang, Sulawesi |
PT. Energy Sengkang |
4 |
Erect 1 Unit of 28.2 Steam Turbine & Generation and its Auxiliaries Equipment for PT. INCO Soroako – East Sulawesi |
Mechanical & Piping |
Soroako, East Sulawesi |
PT. INCO Soroako |
5 |
Installation of Steam Turbine By-Pass Pipe at PT. Freeport Indonesia |
Mechanical & Piping |
Timika, Jayapura |
PT. Freeport Indonesia |
6 |
Erect 2 x 25MW Steam Turbine at PLTU 2 Sulut, Amurang |
Mechanical |
Amurang, North Sulawesi |
PT. P. L. N. |
7 |
Erect 2 x 35MW Steam Turbine at Tonasa Power Plant |
Mechanical |
Makassar |
PT. Tonasa Semen |
8 |
Erect of 2 (two) SST 900 Steam Turbine Generator Sets (STG), including Auxiliary Equipment, Pipe Work and Preheaters |
Mechanical, Piping, Aux & Equipment |
Babelan, Bekasi |
PT. Cikarang Listrindo |